Update from the council:
Over the last four weeks, the works taking place at Dan Bank have been progressing well and are on schedule for completion on Sunday 5th September 2010 in line with the programme.
There has not been any occasion where the road has not been open at 6am and the local bus services have not had any significant delays during the road closure.
As the works are progressing well, no work will take place on Sunday 11th July. This means that Stockport Road will remain OPEN at 7pm Sunday evening and Monday morning.
All electronic signs located on the approach to Dan Bank will be updated on Sunday 11th July to let all those travelling in the area that the road is OPEN.
The scheduled road closure will then continue Monday 12th July from 7pm and electronic signs will read the road is CLOSED.
Stockport Council would like to thank all those who live or work near to Dan Bank and all those who regularly travel along Stockport Road for their patience during these important works. As they continue, we will send further updates letting you know how the works are progressing.