The Civic Society have sent me some information about this to put on the site, infact (apologies to MCS) they sent it a good few days ago and I overlooked it. Basically, this is the information sent by SMBC to local residents near to the site:
To The Current Owner / Occupier
Date: 18th October 2011
My Ref : 08/881/BW/001/LJ
Lee Jamison
Engineering Services,
1st Floor, Fred Perry House
Direct line: 0161 474 4957
Fax: 0161 476 0721
email: l.jamison@stockport.gov.uk
Dear Sir / Madam,
Contract – Chadkirk Bridleway Construction, Marple, Stockport
Stockport Council will be completing an upgrade of the existing Public Right of Way which runs
between Hill Top Drive and the proposed Chadkirk Bridge crossing of the River Goyt to bridleway satus
(see attached plan). The path works will commence on the 24th October 2011 and are anticipated to last
for 23-weeks. To provide appropriate welfare facilities and a storage area a site compound will be set up
within the grassed area at the end of Hill Top Drive. This area will be restored to its original condition
after the completion of the works. The approach paths will be closed from Hill Top Drive, Otterspool
Road and the Dale Farm river side path for the duration of the works. To facilitate access to the work
site it will not be possible to park vehicles along the unsurfaced part of Hill Top Drive adjacent to the
school.
If you would like any further information regarding the above works then please contact me on the
number above.
Yours faithfully
Lee Jamison
Structures Engineer
Enc. Route Plan